Acceptance and handover checklist

What to agree with the vendor before they declare the work complete.

Test case sheets with stamped results

Acceptance is the last moment the client has contractual leverage. Criteria written beforehand stop it from becoming a negotiation.

01

Before execution

Agree in writing:

  • Test cases linked to requirements
  • Test data (dummy, never real production data)
  • Defect classes: blocking, major, minor
  • Acceptance rule (e.g. zero blocking, major with a fix plan)
Binders of handover documentation
02

At handover

Check that you have received:

  • User and configuration documentation
  • List of admin accounts and their holders
  • Contacts and issue-reporting procedure
  • Open defects with expected closing date

Example

Sample test case

Sample test case
CaseRequirementStepsExpected result
T-07aR-07Confirm test order → issue invoiceInvoice with customer, lines and total identical to the order