Acceptance and handover checklist
What to agree with the vendor before they declare the work complete.

Acceptance is the last moment the client has contractual leverage. Criteria written beforehand stop it from becoming a negotiation.
Before execution
Agree in writing:
- Test cases linked to requirements
- Test data (dummy, never real production data)
- Defect classes: blocking, major, minor
- Acceptance rule (e.g. zero blocking, major with a fix plan)

At handover
Check that you have received:
- User and configuration documentation
- List of admin accounts and their holders
- Contacts and issue-reporting procedure
- Open defects with expected closing date
Example
Sample test case
| Case | Requirement | Steps | Expected result |
|---|---|---|---|
| T-07a | R-07 | Confirm test order → issue invoice | Invoice with customer, lines and total identical to the order |